Creation Date In Purchase Requisitions Gets Updated Constantly During Approval (Doc ID 2017378.1)

Last updated on AUGUST 08, 2017

Applies to:

Oracle iProcurement - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Requisition Creation

ACTUAL BEHAVIOR
---------------

The 'creation date' in purchase requisition created in iProcurement, is constantly being updated.

The issue occurs when a document is updated (and consequently unreserved) in the course of approval. From the time it is unreserved, the document's creation date continues to be updated on every approval action taken on it until it is finally approved.


EXPECTED BEHAVIOR
-----------------------
Creation date should be retained at original value

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Navigate to iProcurement
2. Create requisition and Submit for approval
3. Approve > retain creation date
4. Change requisition
5. Check the creation date and compare to the original value.  See the creation date has been updated.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms