Internal Sales Order Not Syncing The Need By Date On Internal Requisition (Doc ID 2022419.1)

Last updated on JULY 19, 2017

Applies to:

Oracle Order Management - Version 12.1.1 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.1

ACTUAL BEHAVIOR
---------------
After applying released patch:19282675:R12.PO.B, the issue still exists in the following case.
The only issue at this moment is whenever trying to pull in the IR NBD further down to the best possible date then
NBD gets updated but the Scheduled Arrival date is not updated causing issue in sync.

IR 926
ISO 10027629
Initial IR NBD 10-Sep-2014
On ISO Creation IR NBD is changed to 20-Oct-2014 which is in Sync with SAD on ISO.
1st Change by Pulling in the IR NBD to 07-Oct-2014
ISO SSD remained unchanged as 15-SEP-2014
ISO SAD remained unchanged as 20-OCT-2014
But the NBD on IR is 07-Oct-2014 causing SAD and NBD out of sync.


EXPECTED BEHAVIOR
-----------------------
1st Change by Pulling in the IR NBD to 07-Oct-2014
ISO SSD remained unchanged as 15-SEP-2014 should be sync according to NBD change
ISO SAD remained unchanged as 20-OCT-2014 should be sync with NBD 07-Oct-2014


STEPS
-----------------------
The issue can be reproduced at will with the following steps:

IR 926
ISO 10027629
Initial IR NBD 10-Sep-2014
On ISO Creation IR NBD is changed to 20-Oct-2014 which is in Sync with SAD on ISO.
1st Change by Pulling in the IR NBD to 07-Oct-2014
ISO SSD remained unchanged as 15-SEP-2014
ISO SAD remained unchanged as 20-OCT-2014

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms