R12:JL:AP: The Due Date Is not Being Calculated Based on the Holidays and/or Weekends as per Brazilian Calendar
(Doc ID 2022983.1)
Last updated on APRIL 04, 2025
Applies to:
Oracle Financials for the Americas - Version 12.1.3 and laterOracle Payables - Version 12.1.3 and later
Information in this document applies to any platform.
Symptoms
On : 12.1.3 version, Brazil AP Globalization
The due date is not being calculated based on the holidays and/or weekends as per Brazilian calendar.
The due date should consider the holidays and/or weekends as per Brazilian calendar.
The issue can be reproduced at will with the following steps:
1. Responsibility: Oracle Payables - Brazilian localization
2. Path: Invoices -> Entry -> Invoices
3. Create an invoice and save.
4. Match the invoice to a PO.
5. Validate the invoice.
6. Pay the invoice.
After recalculating the due date, the terms of the base setup date are ignored.
The due date should consider the holidays and/or weekends as per Brazilian calendar.
There is no issue when the invoice is entered manually in AP.
If the invoice is entered with a due date on the weekend, the system recalculates this date automatically.
The issue has the following business impact:
Due to this issue, users cannot see the correct due date calculated.
Additional symptoms can be seen in:
R12:JL:AP: Receive Error 'Payment Process Request Already Exists' When Entering Payment Process Request Name (Doc ID 2176608.1)
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |