Production Scheduler Workbench Resource Load Required Time Is Including Cancelled Batches.

(Doc ID 2029019.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Scheduler Workbench (Gantt)

ACTUAL BEHAVIOR
---------------
The Production Scheduler Gantt chart is showing resource requirements in the bottom section even though the top section does not show anything scheduled on those resources. The customer believes that it is showing resource requirements from batches that are cancelled.

EXPECTED BEHAVIOR
-----------------------
Expect the resource requirements in the bottom section to match with the resources scheduled at that time and shown in the top section.


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, resource load shown in the bottom section of the Gantt chart are incorrect.

Cause

Sign In with your My Oracle Support account