R12 - Cannot Update Task End Date: 'An Expenditure Item Exists With a Date That is Later Than the End Date of the Task' (Doc ID 2031157.1)

Last updated on JANUARY 14, 2017

Applies to:

Oracle Project Foundation - Version 12.1.3 to 12.1.3 [Release 12.1]
Oracle Project Management - Version 12.1.3 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.

Symptoms

In Projects self service when updating a task as follows: Workplan -> Tasks 

The following error appears: 

"An expenditure item exists with a date that is later than the end date of the task: <task_name>. Please change the task end date to be the same as or later than the expenditure item date: DD-MON-YYYY"

Cause