Min-Max Planning Report Creates Batches Ignoring Workday Calendar (Doc ID 2031195.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Inventory Management - Version 12.1.3 and later
Oracle Process Manufacturing Process Execution - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Batch Creation using Min-Max Planning Report

ACTUAL BEHAVIOR
---------------
When using the Min/Max Planning Report to create OPM batches, the batches are created as if there is a 24x7 workday calendar. When creating the same batch manually, the workday calendar is correctly used. Because of this, the duration of the batches created from Min/Max Planning is incorrect, it is too short.

It is as if the report is telling the batch creation API to ignore the workday calendar.

EXPECTED BEHAVIOR
-----------------------
Expect the workday calendar to be honored when batches are created from the Min/Max Planning Report.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a workday calendar that has shifts that add to less than 24 hours a day and link it to the org.
2. Use the Min/Max Planning Report to create batches.
3. Compare those batches to ones created manually.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, batch durations are incorrect for batches created from Min/Max Planning.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms