Discrete Job Backward Completion Date Changes When Backward Scheduling from Completion Date (Doc ID 2033352.1)

Last updated on DECEMBER 08, 2015

Applies to:

Oracle Work in Process - Version 12.2.3 to 12.2.4 [Release 12.2]
Information in this document applies to any platform.

Symptoms

Discrete Job Backward completion date is not calculating correctly.



STEPS

The issue can be reproduced at will with the following steps:

1.   Responsibility: Work in Process

2.   Navigate: Discrete - Discrete

3.   Enter Discrete Job Manually

4.   Enter Completion date (e.g., 20-Jun-2015)

5.   Enter Assembly item and Quantity

6.   Save the Discrete job

7.   Automatically Start Date is populating

8.   Now Change the Alternate Routing

9.   System populating 'Schedule Discrete job'

10. Choose 'Backward from completion Date'

11. System automatically changing the 'Completion' Date and Start Date

12. But expectation is system should calculate the Start date by keeping Completion date Constant

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms