Work Orders Without Labor Cost
(Doc ID 2033684.1)
Last updated on APRIL 08, 2025
Applies to:
Oracle Cost Management - Version 12.0.6 and laterInformation in this document applies to any platform.
Symptoms
Work orders without labor cost -> there are many work orders completed and labor applied but the cost of labor equal Zero in Work Order Value Summary form (no pending/error transactions for this exist)
Since work order has transactions with cost associated should be able to see relevant cost in Work Order Value Summary form (Actual Labor Cost)
The issue can be reproduced at will with the following steps:
1. create work order
2. charge resources apply cost
3. complete work order, transactions costed but not actual labor cost presented in Work Order Value Summary form
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |