Lot Costing Issue With Outside Processing Item (OSP) on Batch - Always uses Resource Cost and Not Purchasing Price Irrespective of Setup (Doc ID 2042269.1)

Last updated on NOVEMBER 03, 2016

Applies to:

Oracle Process Manufacturing Financials - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, Lot Costs

ACTUAL BEHAVIOR
---------------


Lot costing always uses an OSP resource cost never the PO Cost even though the resource is set up to use PO Price.

Actual Costing uses the Purchasing Price whereas Lot Costing always uses the Resource Cost from the batch Step irrespective of setup.

EXPECTED BEHAVIOR
-----------------------


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Production Supervisor>Create a batch for a new product using a new OSP item as an ingredient.
2. Receive OSP item.
3. Run Lot Costing and Actual Costing
4. Compare the costs.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, batch costs are incorrect and so costs and financial results cannot be completed for the period.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms