My Oracle Support Banner

Child Flow Schedules Created With Incorrect Quantity By Conc. Prg "Feeder Line Synchronisation" (Doc ID 2043645.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Flow Manufacturing - Version 12.1.3 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.

Symptoms

When attempting to synchronize flow schedules, the planned quantities for child schedules is incorrect.  The issue (incorrect quantity) happens only for units having a subassembly (the same item number) multiple times.

ERROR

Flow schedule quantities should be correct

STEPS

The issue can be reproduced at will with the following steps:
1.  Flow Manufacturing: Line Scheduling-> Line Scheduling Workbench create flow schedule for org / assembly.  Note that the assembly must have the same phantom subassembly appearing in the Bill Of Materials (BOM) multiple times
2.  Flow Manufacturing: Line scheduling Feeder Line Synchronization
3.  From Line A to A
4.  Multiple child flow schedules are created for parent and the total quantity is much more than the the required quantity

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.