Symptoms

When attempting to synchronize flow schedules, the planned quantities for child schedules is incorrect.  The issue (incorrect quantity) happens only for units having a subassembly (the same item number) multiple times.

ERROR

Flow schedule quantities should be correct

STEPS

The issue can be reproduced at will with the following steps:
1.  Flow Manufacturing: Line Scheduling-> Line Scheduling Workbench create flow schedule for org / assembly.  Note that the assembly must have the same phantom subassembly appearing in the Bill Of Materials (BOM) multiple times
2.  Flow Manufacturing: Line scheduling Feeder Line Synchronization
3.  From Line A to A
4.  Multiple child flow schedules are created for parent and the total quantity is much more than the the required quantity

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.