Some Requisition Lines Are Grouped When Adding Requisition Lines To An Existing RFQ. (Doc ID 2044098.1)

Last updated on AUGUST 21, 2016

Applies to:

Oracle Sourcing - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, Auction/RFx creation

Requisition lines are grouped when adding requisition lines to an existing RFQ.

The expected behavior is the application must create individual lines in the RFQ when adding the lines to RFQ.

Due to this issue, users are not able to see the requisition lines created as lines are getting merged.

Steps To Reproduce
1. Log in to Purchasing Responsibility.
2. Create a Non Catalog Request with different items with different item descriptions.
3. Approve requisition.
4. Navigate to Sourcing responsibility and create RFQ by adding 3 requisition lines from above created Requisition.
5. Now add 3 more lines to the existing RFQ.
6. When the RFQ is viewed, 2 lines are getting merged to single RFQ.



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms