UOM Conversion Decimal Issues When Creating Batch in Secondary UOM Using Total Output Quantity (Doc ID 2044914.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, Setup Issues

ACTUAL BEHAVIOR
---------------
When creating a batch using secondary UOM, there is decimal dust in planned quantity.

1) Item are defined using Dual UOM Primary Pounds Secondary Each.
2) OPM Batch is created using Total Input for 20 Each.
3) The Plan Quantity should be 107900 LBS and not 107900.00108

EXPECTED BEHAVIOR
-----------------------
Expect planned quantity to be whole number based on conversion and not have decimal dust.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Production supervisor > batches



Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms