Goal

In Project Costing, a user entered a zero cost rate for an HR Job and entered a timecard pre-approved batch.
The resource used has the HR Job with the zero cost rate.
The user was able to distribute labor costs without an error and ran the create cost events and create accounting.
When reviewing the data at the Cost Distribution Lines level in Expenditure Inquiry; the Distribution Line Status is Accepted.
Is costing with a zero cost rate intended functionality?
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.