Date in Service for Assets Created Through Project Is Different from Date in Service Entered in Deployment Page (Doc ID 2051237.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Asset Tracking - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms


Asset is created with date in service = deployment source reference date rather actually date in service.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. PO receive an instance to project
2. Install the instance
3. Put in service, enter different date in field Date in Service than source reference date
4. Run 'Interface In-service to project'
5. Run "Create Asset Headers in Oracle Projects - Normal Items"
6. Run PRC: Generate Asset Lines for a Single Project
7. Run PRC: Interface Assets to Oracle Assets
8. Run Mass Additions Post
9. Check asset in asset workbench

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms