MSP Doesn't Bring in The 'Override Raw Cost Rate' so the Cost Calculation Are Wrong (Doc ID 2052149.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

When there is an Override Raw Cost Rate assigned to any resource, MS Project never brings in this rate.  Therefore, the calculation of costs per resource and task are wrong.

Cause