Material & Serial Labels Do Not Populate Project & Task Correctly When Multiple Distributions Are Used
(Doc ID 2053528.1)
Last updated on SEPTEMBER 06, 2021
Applies to:
Oracle Warehouse Management - Version 12.2.3 and laterInformation in this document applies to any platform.
Symptoms
With standard receipt and inspection required, project and task are not populated on MATERIAL label
Regardless of the receipt routing, project and task is picked up from the first serial on SERIAL label and thus wrong.
Steps
Create a PO shipment with 2 distributions with different project & task for a serial controlled item and perform the putaway in one receipt.
You will see that the serial label will take the project & task from the first line.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |