Preventive Maintenance (PM) Schedule Does Not Generate Next Work Order After Previous Work Order Completion (Doc ID 2053760.1)

Last updated on OCTOBER 23, 2015

Applies to:

Oracle Enterprise Asset Management - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms



ACTUAL BEHAVIOR

PM schedule failed to generate the next work order after the scheduled work order has been completed. This is only happening with two PMs and the rest of the PMs are working fine.


EXPECTED BEHAVIOR

Expect that all PM schedules to generate work orders.


STEPS

The issue can be reproduced with the followings steps:

1.  Responsibility: Enterprise Asset Management.

2.  Navigation:  Work Order Planning -> Maintenance Workbench.

3.  Enter Asset Number.

4.  Click Launch button.

5.  Perform forecast work order.

Cause

Sign In with your My Oracle Support account