Avoid Auto Completing Batch Product Line when the Batch is Closed (Doc ID 2054351.1)

Last updated on NOVEMBER 03, 2016

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Batches

ACTUAL BEHAVIOR
---------------
Auto completion of a batch product line

When changing the status from WIP to complete a product line is automatically completed

EXPECTED BEHAVIOR
-----------------------

That the product line is not automatically completed.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Production Supervisor
2. Batches
3. Query back batch and complete it

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, a batch production has a product line that has been completed automatically when the batch is completed and this means that the lot produced my not be the correct causing inventory to be incorrect.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms