R12: Mass Update Progress Does Not Change Task Status And Actual Start Date (Doc ID 2058224.1)

Last updated on SEPTEMBER 01, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

In Workplan -> Tasks, if task status is changed for a subtask which was previously 'Not started,' and then the Mass Update Progress is submitted, everything is correct.  However, if the task status change is reverted and Mass Update Progress is submitted again, the result is that the parent task status is not changed back to 'Not started' and shows an Actual Start Date.

Cause

Sign In with your My Oracle Support account