Symptoms

On : 12.1.3 version, Users are unable to forecast work orders for some asset numbers  in Maintenance Work bench for some cut-off days

Example
For a specific Asset number if user chooses any date before 10-OCT-2015 as end date no work orders are forecasted.
However if user chooses any date before 10-OCT-2015 as end date the work orders are suggested from current date.

EXPECTED BEHAVIOR: Expect to have forecast work orders generated


The issue can be reproduced at will with the following steps:

1. forecast form enter 04-08-15 and cut off date : 15-09-15 => horizon: 42  > In this case work orders are not forecasted.
2. with same start date and cut off date: 18-Oct-15 => horizon: 75 days > have forecast work orders presented
 



Cause

Sign In with your My Oracle Support account