Applies to:

Oracle Process Manufacturing Process Planning - Version 11.5.10.2 and later
Information in this document applies to any platform.

Goal

We need to find out if there is a way to set MRP to only consider items and formulas from the company and plant for which it is being run.
Currently MRP execution ends with status = Stop as it finds multiple errors related to inconsistencies with formulas from other companies.
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.