Work Orders Scheduling On The Weekend Instead of Week Day When Scheduling Via Backward Scheduling (Doc ID 2067915.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Work in Process - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

Enter a completion date on a new work order. Oracle schedules the start date on a Saturday. It should be a weekday, not the weekend.

EXPECTED BEHAVIOR

Start Date should not default to Weekend.

STEPS

The issue can be reproduced at will with the following steps:
1. Responsibility: Work in Process
2. WIP - Discrete - Discrete
3. Enter a Completion Date and save the work order.
4. Start Date gets defaulted to Weekend.

Cause