R12 PSI Does Not Export Costs Greater Than 2 Decimals of Precision For Open Commitments (Doc ID 2071850.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

In : 12.1.3 version, Project Performance Reporting

In 11i, Project Status Inquiry (PSI), would export the penny fractions for open commitments that didn’t have a price on the PO for. Now, in R12, it does not do that and only passes a flat zero.

The “raw_cost” and “burdened_cost” columns store the information between 11i and R12 differently so that the Export function does not show more than 2 decimal places, which gets rounded to 0.

 