R12.2.3 - Getting Signal 11 Error in WIP Concurrent Exploder Program Due to Incorrect Date Format (Doc ID 2078185.1)

Last updated on DECEMBER 27, 2016

Applies to:

Oracle Work in Process - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

Problem Statement
When attempting to run WIP Concurrent Exploder, the folloiwng error can be found in concurrent log.

Error
  Job will be scheduled using resource utilization
 Job will be scheduled using resource efficiency
/xxxx/yyyy/appl/zz1/EBSapps/appl/wip/12.0.0/bin/WICMEX
Program was terminated by signal 11

Steps to Reproduce

  1. Run WIP Concurrent Exploder

Cause