Military Interdepartmental Purchase Requests (MIPR) Obligation Type Resets To Default Value When Creating A Requisition Amendment (Doc ID 2086630.1)

Last updated on DECEMBER 28, 2015

Applies to:

Oracle Contract Lifecycle Management for Public Sector - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.3 version, Requisition

ACTUAL BEHAVIOR
---------------
MIPR type requisitions have a MIPR Obligation Type column at the line level where users can choose one of these three values - Both, Reimbursement, and Direct Citation. The agencies create multi-line MIPRs assigning different MIPR obligation type values.

When creating an amendment to a MIPR, the MIPR obligation type value changes to the default value (Both) for all lines.

EXPECTED BEHAVIOR
-----------------------
Expect to keep the same MIPR Obligation Type value as entered in the requisition

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Navigate to Contract Lifecycle Management (CLM) iProcurement.
2. Create a multi-line MIPR and assign different MIPR obligation type values to each line and approve the requisition.
3. Create amendment and verify the value of MIPR Obligation Type for each line, it resets to default,

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms