Error "Line 1, Pay Item 0 - Percentage must be between 0 and 100" Coming While Adding Advance In PO (Doc ID 2089935.1)

Last updated on DECEMBER 18, 2015

Applies to:

Oracle Purchasing - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

When attempting to add Advance in complex PO,
the following error occurs.

Error:
Error : Line 1, Pay Item 0 - Percentage must be between 0 and 100.


Replication Steps:
The issue can be reproduced at will with the following steps:
1. create a complex PO
2. Add a Advance amount.
3. Save the details. Getting the error when saving.

 

Cause

Sign In with your My Oracle Support account