R12: Total To Date Costs Not Calculated Correctly In Cost-to-Cost Revenue Extension (Doc ID 2093980.1)

Last updated on JANUARY 04, 2016

Applies to:

Oracle Project Billing - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms


ACTUAL BEHAVIOR
---------------
Issue is with formula of Oracle “Cost-to-Cost Revenue” extension, where the AC amount calculated by the extension is wrong. This occurs when the projects are burdened.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run PRC: Generate Draft Revenue for a Range of Projects using the Oracle “Cost-to-Cost Revenue” extension .


Cause

Sign In with your My Oracle Support account