PAXINVPF: Project Funding Is Not Equal To The Budget Total. To baseline a draft budget, the budget total must be as same as funding total. (Doc ID 2096640.1)

Last updated on JANUARY 20, 2024

Applies to:

Oracle Project Billing - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Unable to baseline funding. Getting below error -
Error: Project funding is not equal to the budget total. To baseline a draft budget, the budget total must be as same as funding total.


Changes

 

Cause