Symptoms

On EAM - Enterprise Asset Management, 12.1.3 version, PM - Preventive Maintenance

ACTUAL BEHAVIOR
-----------------------
After resequence in maintenance workbench, the action is not changed to No Action but remains with Resequence.

EXPECTED BEHAVIOR
-----------------------
Expecting the action to get changed to No Action

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Enterprise Asset Management responsibility
2. Work Order Planning > Maintenance Workbench
3. Launch the WB for a particular asset and activity
4. Perform the forecast.
5. Select the first record to resequence and implement.
6. The same record will remain with action "Resequence"

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms