Unable to Close WIP Job: "Number of jobs failed in Delivered Quantity: 1" or "Quantity delivered less than Quantity received"
(Doc ID 2098849.1)
Last updated on MARCH 08, 2024
Applies to:
Oracle Inventory Management - Version 12.1.3 and laterOracle Work in Process - Version 12.0.0 and later
Information in this document applies to any platform.
Symptoms
When attempting to close a specific discrete job, the following error occurs.
The following error is observed in the Close Discrete Job program log file (WICDCL log file):
Number of jobs failed in Delivered Quantity: 1
Job ends in status Failed Closed.
Quantity delivered less than Quantity received
Number of jobs failed in Delivered Quantity : 1
Steps to Reproduce the Issue:
--------------------------------------
1. Responsibility: Work In Process.
2. Discrete Job > Close Discrete Job > Close Discrete Job (form).
3. Enter job details.
4. Note message seen "PO/Requisition was not automatically cancelled. Cause: PO/Requisition cannot be cancelled if: 1. PO/Requisition was in a status other than Approved, or Rejected. 2. PO/Requisition was already closed, or finally closed, or cancelled, or put on hold. &Message (Message=) The specified control action (Action = CANCEL) is invalid for this document. &MESSAGE (MESSAGE=) The specified control action (ACTION = CANCEL) is invalid for this document. PO.PO_CONTROL_INVALID_ACTION N ACTION CANCEL. The specified control action (Action = CANCEL) is invalid for this document."
5. Button: OK
6. Menu: Tools
7. Close 1 > Detailed report
8. Concurrent program completes error.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |