Pa_status_pub.Update_Earned_Value Creates Records With Wrong Creation Date‏ (Doc ID 2102288.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Foundation - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Using the api pa_status_pub.Update_Earned_Value, when a user creates more than one set of records for a project and task for the same as_of_date the subsequent records created use the same creation and update date as that of the first records created for project and task. This is causing issues for earned value reporting in that it is impossible to identify the correct records as the project/tasks/as of date and creation dates are duplicated. From a reporting perspective, the latest creation dates for the as of date is desired.


Cause

Sign In with your My Oracle Support account