Incorrect Forecast ETC Calculation When Open Commitments Exists

(Doc ID 2103933.1)

Last updated on SEPTEMBER 13, 2016

Applies to:

Oracle Project Planning and Control - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

When generate a new forecast version in a project using the below parameters, the calculation is not correct in the ETC field or Forecast amount field, for any manual changes in the forecast editing page.

a) in the Forecast Generation options:

     - ETC Source: Task level Selection

     - Open Commitments selected

b) in the financial tasks:

     - ETC Method = Remaining Plan

 

Cause