Unable To Update Contract Terms If Contract Source Is Attached Document (Doc ID 2103979.1)

Last updated on FEBRUARY 13, 2019

Applies to:

Oracle Procurement Contracts - Version 12.2.4 to 12.2.5 [Release 12.2]
Information in this document applies to any platform.

Symptoms

Find that it is not possible to update the Contract Terms if the Contract Source is Attached Document

Creating an RFQ, in the Contract Terms section, if a Contract Template is not applied and instead Contract Source is an Attached Document, and no Primary Contract Document has been uploaded, there is no way to remove or change or apply a new template or a new document.

Expected Behavior:
Expect to be able to change or remove the uploaded document or add a contract template to the new RFQ or PO.

Steps to Reproduce:
1. Navigate to Sourcing
2. Create an RFQ
3. Apply a template
4. Save as draft
5. Click on Contract Terms on the left
6. Update Contract Details
7. Contract Source > Attached Document
8. Apply
9. Cannot apply a contract template nor remove the uploaded document
10. Click on Review
11. Go to Contract Terms Tab
12. Click on update
13. This takes the user back to the previous screen where there is no place to remove the attached document or add terms

Business Impact:
Due to this issue users cannot remove attached docs.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.