Generating Forecast Budget The Amount Fields Are 0 (Doc ID 2108731.1)

Last updated on FEBRUARY 19, 2016

Applies to:

Oracle Project Foundation - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, Organization Forecast

When trying to generate a forecast based on a previously approved cost budget, in the new forecast version that's generated, the "Current Budget" amounts are all showing up as $0 under raw, burdened, quantity and all columns.

The actuals come in correctly based on what's charged to that task/resource. However it seems the budgeted amounts are sent to the ETC field and Forecast is entered as Actual+ETC.

Cause