Flow Schedule Completion Transactions Erred In MTL_TRANSACTIONS_INTERFACE

(Doc ID 2115242.1)

Last updated on MARCH 18, 2016

Applies to:

Oracle Flow Manufacturing - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.4 version, FLOW

When attempting to perform completion trough the MTL_TRANSACTIONS_INTERFACE, the following error occurs.

This line, schedule group, build sequence combination is already being used by another job or flow



The issue can be reproduced at will with the following steps:
1. add records in interface
2. process and observe error



Cause