Release Management (RLM) Net Change Report Creating Incorrect Data Comparisons and Cumulative (CUM) Calculations

(Doc ID 2115485.1)

Last updated on MARCH 25, 2016

Applies to:

Oracle Release Management - Version 12.1.3 and later
Information in this document applies to any platform.


On : 12.1.3 version, Reports related Issues

Observation, believe something is wrong with this Net Change Report. Ran the RLM Net Change Report
to compare two RLM 830 Schedules. The New file contains 3 Firm Demand Lines for one date and 3 lines
for a 2nd date. Same for the 'old' file, however, the Net Chance Report is showing 5 lines instead of 3 for
first date and also incorrect CUM calculations for both new and old. It is also showing 4 comparison dates
for date 2.

RLM Schedule shows only 3 lines for 13-Nov therefore the expectation is that the
Net change Report would show the same 3 lines but instead it shows 5 lines.
1. Responsibility: Release Management
2. Run > Net Change Report
    New Schedule: 151112E
    Old Schedule: 151112D
3. Observe: 5 lines present, expected 3 lines


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms