Unable To Mass Update Progress Via API - pa_progress_pub.update_task_progress (Doc ID 2119633.1)

Last updated on OCTOBER 22, 2016

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Public API's

Unable to mass update Progress via API

Customer is uploading the Progress of the Projects via standard Oracle API pa_progress_pub.update_task_progress .

When trying to update the Estimated , Actual Start and completion dates , Completion Percent ,the API is throwing the below error:

ERROR
-----------------------
The As of Date is invalid. Please check the Progress Cycle of the project. (AS_OF_DATE=08-MAR-2016)