Symptoms

Depreciation amount in the last period of the year is calculated by mistake using revised rate when performing Impairment.

Condition

Steps to Reproduce
1.  2015-03 *** Addition

    Cost                               : 206294
    YTD depreciation                   : 17731
    Accumulated depreciation           : 151262
    Date in Service                    : 01-OCT-2008
    Depreciation method                : JP-250DB 7
    Salvage value                      : 0
    Depreciation limit amount          : 1


2.  2015-03 *** Override

    Period Name         : 2015-03
    Deprn Amount        : -10
    Used by             : DEPRECIATION
    Status              : Post


3.  2015-03 *** Impairment

    Impairment amount   : 35301


4.  2015-04 *** Change Depreciation method to JP-250DB 5 with Amortized

    Depreciation method             : JP-250DB 7 --> JP-250DB 5
    Amortized flag                  : Yes
    Amortization start date         : 01-APR-2015


5.  2016-03 *** Check the Asset

    FA_BOOKS ***
    COST    ADJUSTED_COST  DEPRN_METHOD  RATE
    ------  -------------  ------------  -----
    206294          72763  JP-250DB 7    0.357
    206294          19741  JP-250DB 7      0.5
    206294          19741  JP-250DB 5      0.5  <--- Original rate

    FA_DEPRN_SUMMARY ***
    PERIOD    COUNTER   DEPRN_AMOUNT   DEPRN_RESERVE   ADJUSTED_COST
    -------   -------   ------------   -------------   -------------
    2015-02     24179              0          151262           72763 <--Using original rate
    2015-03     24180            -10          151252           55042 <--Using original rate
    2015-04     24181            823          152075           19741 <--Using original rate
    2015-05     24182            823          152898           19741 <--Using original rate
    2015-06     24183            823          153721           19741 <--Using original rate
    2015-07     24184            823          154544           19741 <--Using original rate
    2015-08     24185            823          155367           19741 <--Using original rate
    2015-09     24186            823          156190           19741 <--Using original rate
    2015-10     24187            823          157013           19741 <--Using original rate
    2015-11     24188            823          157836           19741 <--Using original rate
    2015-12     24189            823          158659           19741 <--Using original rate
    2016-01     24190            823          159482           19741 <--Using original rate
    2016-02     24191            823          160305           19741 <--Using original rate


6.  2016-03 *** Impairment

    Impairment amount   : 1


    FA_BOOKS ***
    COST    ADJUSTED_COST  DEPRN_METHOD  RATE
    ------  -------------  ------------  -----
    206294          72763  JP-250DB 7    0.357
    206294          19741  JP-250DB 7      0.5
    206294          19741  JP-250DB 5      0.5
    206294           9041  JP-250DB 5        1 <--Correct. This rate will be used in the next year.

    FA_DEPRN_SUMMARY ***
    PERIOD    COUNTER   DEPRN_AMOUNT   DEPRN_RESERVE   ADJUSTED_COST
    -------   -------   ------------   -------------   -------------
    2015-02     24179              0          151262           72763 <--Using original rate
    2015-03     24180            -10          151252           55042 <--Using original rate
    2015-04     24181            823          152075           19741 <--Using original rate
    2015-05     24182            823          152898           19741 <--Using original rate
    2015-06     24183            823          153721           19741 <--Using original rate
    2015-07     24184            823          154544           19741 <--Using original rate
    2015-08     24185            823          155367           19741 <--Using original rate
    2015-09     24186            823          156190           19741 <--Using original rate
    2015-10     24187            823          157013           19741 <--Using original rate
    2015-11     24188            823          157836           19741 <--Using original rate
    2015-12     24189            823          158659           19741 <--Using original rate
    2016-01     24190            823          159482           19741 <--Using original rate
    2016-02     24191            823          160305           19741 <--Using original rate
    2016-03     24192           1646 <--Wrong 161951            9042 <--Wrong.  It is using revised rate.



    Current behavior
    Theoretical YTD
        = trunc(adjusted_cost * Rate in use)
        = trunc(adjusted_cost * Revised rate)
        = trunc(19741 * 1)
        = 19741

    Period Depreciation
        = round(Theoretical YTD * (1/12))
        = round(19741 * (1/12))
        = 1645


    Depreciation amount is calculated by mistake using revised rate


    Expected behavior
    Theoretical YTD
        = trunc(adjusted_cost * Rate in use)
        = trunc(adjusted_cost * original rate)
        = trunc(19741 * 0.5)
        = 9870

    Period Depreciation
        = round(Theoretical YTD * (1/12))
        = round(9870 * (1/12))
        = 823


     Depreciation amount in 2016-03 should be 823, instead of 1645

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms