When Rescheduling from Parent Batch, Phantom Batch Planned Start Date Does Not Change
(Doc ID 2128097.1)
Last updated on AUGUST 11, 2022
Applies to:
Oracle Process Manufacturing Process Execution - Version 12.2.4 and laterInformation in this document applies to any platform.
Symptoms
On : 12.2.4 version, Batches
ACTUAL BEHAVIOR
---------------
When rescheduling both Planned Start and Planned Completion Dates on a parent batch, the Planned Start Date on phantom batches are not updated, although the Planned Completion Date is updated.
EXPECTED BEHAVIOR
-----------------------
Expect both dates to be updated on the phantom as well as the parent.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a parent and phantom batch.
2. Reschedule the parent batch.
BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, planned start date on phantom batches are wrong.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |