R12.2 OPM Batch Release Last Batch Step, Reserved Qty Becomes Actual Qty When Wip Plan Qty=0 (Doc ID 2128364.1)

Last updated on APRIL 18, 2016

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
Batch ingredient consumption type and product yield type are both 'Automatic by step'.
Update WIP plan quantity to 0 and release the step 500, then its doing back flush of reserved quantity instead of WIP plan quantity.
if WIP is 0 and reserve qty >0
then
take reserve qty for back flush
else
take WIP qty for back flush


EXPECTED BEHAVIOR
if WIP qty < reserved qty
then take WIP plan qty for back flush
else
take the reserved qty first then and try to get more qty if WIP qty is greater than reserve qty.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Update WIP plan quantity to 0 and release the step 500
2. Saw the issue.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms