Budgetary Controls Not Working For CLM PARs When Using Project And GL Budgetary Control

(Doc ID 2140702.1)

Last updated on MAY 21, 2016

Applies to:

Oracle Purchasing - Version 12.2.4 and later
Information in this document applies to any platform.

Symptoms

The funds check for CLM PARs is completing successfully, even though there are insufficient funds for the specified project task combination.
 Budgetary control Funds Check level=Absolute
Receiving no  warnings or hard errors when running the funds check for PARs.
Successfully Approving despite no funds available

 Federal Purchasing AAD
Funds Check level =Absolute



Cause