EAM Resource Cost Not Included In Work Order Estimate (Doc ID 2146107.1)

Last updated on JUNE 06, 2016

Applies to:

Oracle Enterprise Asset Management - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Construction Units & Estimates

ACTUAL BEHAVIOR
---------------
Adding New resource in the Work order and re-estimate , the value remain the same ( Resource cost is not added to the calculation).

EXPECTED BEHAVIOR
-----------------------
Re-estimate need to add all the values mentioned in the Work order both Materials and Labor costs.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1.
2. 3.
4.
5. < The Value is not included in the Calculation >


Cause