OPM R12.2 How To Change Sample Disposition From "In Progress" To "Accept With Variance" Using API

(Doc ID 2150737.1)

Last updated on FEBRUARY 28, 2018

Applies to:

Oracle Process Manufacturing Product Development - Version 12.2.4 and later
Information in this document applies to any platform.

Goal

How to change Disposition from "In Progress" to "Accept With Variance" using API?

From Application,we are following the below navigation to change disposition status.
Quality Manager Responsibility>Results>Results>
Query for the sample number-->Entering values for Results>save.
Actions>Change Disposition.
It's able to change disposition status from "In Progress" to "Accept With Variance" in application.
 

Solution