R12: PA: Options to Calculate EAC and ETC at Project Level? (Doc ID 2151786.1)

Last updated on JULY 25, 2016

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

1) Is there is an option to view the Estimate to Complete (ETC) at project level using the different method that exists as when you create the forecast? In the project list page, there is a column name ETC but the value calculated here is : ETC: Forecast - Actual Cost.

2) Is there an option to calculate ETC with the formula ETC = EAC - Actual Cost ; Where EAC = Budget At Completion / CPI? If so, how can this be achieved?

 

Solution