Changing Need-by Date or Project Information for Multiple Lines are not Set to Edit and Submit Requisition Page (Doc ID 2156182.1)

Last updated on OCTOBER 17, 2016

Applies to:

Oracle iProcurement - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

Actual Behavior
The changed Need-By Date or project information value is not set to Edit and Submit Requisition page after applying patch:23050151.


Expected Behavior
The changed Need-By Date or project information value should be set to Edit and Submit Requisition page.

Steps to Reproduce

  1. Add item to cart
  2. click View Cart and Checkout
  3. Edit
  4. select line and click Update
  5. change Need-by Date or project information
  6. Apply
  7. return to Edit and Submit Requisition page
  8. The Need-by-Date is not changed

Changes

 Applying patch:23050151

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms