Subcontracting: Interlock Manager Processes Many PO Requests - But The Parameter Was Set To Process Only 1 New PO (Doc ID 2156368.1)

Last updated on AUGUST 14, 2016

Applies to:

Oracle Outsourced Mfg for Discrete Industries - Version 12.2.4 and later
Information in this document applies to any platform.

Goal

When we are running "Subcontracting: Interlock Manager" for one PO , It running for all the PO in our system ,

For example:
Run the "Subcontracting: Interlock Manager" with parameters set for single PO No 1863 , This PO having finished good OSAssy1 and the finished good having three components OSComp1, OSComp2, OSComp3
We expect this to generate 3 Import Standard Purchase Orders requests that are needed to create 3 Replenishment PO for the components. But we see it picks up all other outstanding PO in the system and runs 263 "Import Standard Purchase Orders" requests.

We do not want to process other POs , as we have not received supplies for these components so they can be processed successfully.
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms