Supplier On Hold But Still Able To Raise A Requisition (Doc ID 2162897.1)

Last updated on AUGUST 01, 2016

Applies to:

Oracle iProcurement - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When putting a supplier on hold user's are still able to raise iProcurement requests.

 

EXPECTED BEHAVIOR

It is expected that putting a supplier on hold will prevent requisition from going through.

 

STEPS

The issue can be reproduced at will with the following steps:
1. Put Supplier on hold
2. Create a requisition
3. Requisition goes through successfully

Cause