Wrong Transaction Date For Step Completion Event Created By Outside Processing Resource (Doc ID 2164518.1)

Last updated on JULY 27, 2016

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.2.5 and later
Information in this document applies to any platform.

Symptoms

On Application Release 12.2.5:

ACTUAL BEHAVIOR
---------------
Batch is created, Requisition and PO are created, then PO for Outside Processing Item is received entering a specific date in the past, Resource Transaction processor and all OPM Costing Processes are run. When Detailed Subledger is run, we can see that transaction date is OK for Receive to Inspection event and it is wrong in Step Completion event for the Outside Processing Resource. This has a huge impact because my client will create backdated PO Receipt transactions for Outside Processing items and in some cases transaction will be created in a period and user will enter a transaction date in a previous period. Furthermore for one PO Receipt, transaction date was created with system date for another one was created with a backdated transaction, but any of them was created with the transaction date entered in Receipt Header form when doing the receipt.

EXPECTED BEHAVIOR
-----------------------
The customer expects to see that when the Detailed Subledger Report is run it has the correct transaction date (transaction date entered in Receipt Header form when performing the receipt = Receipt date: 05/31/2016 23:00:00) for the Event Type Receipt to inspection and Event Type Step Completion for the Outside Processing Resource.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

The customer provided the following sequence of events-
1. Responsibility: Production Supervisor
2. Batch is created, Requisition and PO are created, then PO for Outside Processing Item is received entering a specific date in the past.
3. Resource Transaction processor and all OPM Costing Processes are run.
4. When Detailed Subledger is run, notice the transaction date is OK for Event Type Receive to Inspection and it is wrong in Event Type Step Completion for the Outside Processing Resource.
 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms