Generate Cost Forecast From Published Version Workplan Uses Remaining Plan And Not ETC Method (Doc ID 2164602.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Generate cost forecast from published version workplan does not use workplan resource ETC method

Cause