PO_CUSTOM_Package Is Called When Updating A Requisition (Doc ID 2170111.1)

Last updated on FEBRUARY 24, 2019

Applies to:

Oracle iProcurement - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Requisition Creation

ACTUAL BEHAVIOR
---------------
when we update a requisition from a approval notification (requisition status is inprocess) and the GL date is updated by the system because the requisition was created in the previous month that has been closed, the po_custom_pkg for defaulting distribution lines is recalled.

EXPECTED BEHAVIOR
-----------------------
Expected was that the defaulting functionality is called only when creating a requisition.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a Requisition with a GL date in period A
2. Change defaulted value of the DFF Cost Center to <Cost Center1>
3. Submit for approval
4. Close the PO period A and open the next period
5. Open the notification for Approval
6. Edit requisition
7. Approver check out
8. The value for the dff Cost Center has been defaulted back to <Default Cost Center> it should remain <Cost Center1>.


BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot remember what the previous value was changed to.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.